top of page
Coca-Cola Bottling Plant
Baku/Azerbaijan
Founded on a 30.000 m2 brownfield area in Baku, Azerbaijan. The sloped topography and ground conditions of the site caused particular difficulties for the settlement of factory. Also, project was constructed under the limitations of tough specifications due to presence of old oil wells on the site.

Following construction types have been used:

Steel building structure, R.C. Pile Foundations , Conventional heavy reinforced concrete construction Cold rolled , coilcoated metal roofing andfacade cladding systems High standart finishing systems and electro-mechanical systems.

 

Facilities:

Administration Building: 1.000 m2

Main Building:13.600 m2(Production, Filling, Storage)

 

Employer: Coca-Cola Baku Bottling Co..

Investment amount: 24.000.000 USD

Construction area: 14.000 m2

Building ground area: 13.000 m2